MANDT
Client
CLNT
3
0
T000
MANDT
BEDID
ID of the Capacity Requirements Record
NUMC
12
0
KBKO
BEDID
BEDZL
Internal counter
NUMC
8
0
CIM_COUNT
CANUM
Counters for cap. rqmts. records (various caps. + indiv.caps
NUMC
4
0
CY_COUNT
ARBID
Work Center ID
NUMC
8
0
ARBPLATZ
TYPKZ
Category of object causing the load (order category)
CHAR
1
0
TYPKZ
Possible values
1
Work orders (detailed scheduling / routing...)
2
Planned orders (detailed scheduling / routing...)
3
SOP-Order (detailed scheduling / routing...)
A
Maintenance task
B
Maintenance messages
OBJKZ
Indicator: Remaining split record
CHAR
1
0
OBJKZ
Possible values
KAPID
Capacity ID
NUMC
8
0
KAKO
KAPID
BEDKZ
Indicator: Remaining split record
CHAR
1
0
BEDKZ
KRUESOLL
Scheduled Capacity Requirements for Setup
FLTP
16
16
CY_KRUESOL
KRUEREST
Remaining Capacity Requirements for Setup
FLTP
16
16
CY_KRUERES
KBEASOLL
Scheduled Capacity Requirements for Processing
FLTP
16
16
CY_KBEASOL
KBEAREST
Remaining Capacity Requirements for Processing
FLTP
16
16
CY_KBEARES
KABRSOLL
Scheduled Capacity Requirements for the Teardown
FLTP
16
16
CY_KABRSOL
KABRREST
Remaining Capacity Requirements for Teardown
FLTP
16
16
CY_KABRRES
KEINH
Unit of Measure for Capacity Requirements
UNIT
3
0
T006
CY_KEINH
FSTAD
Earliest Start Date
DATS
8
0
FSTAD
FSTAU
Earliest Start Time
TIMS
6
0
FSTAU
FENDD
Earliest End Date
DATS
8
0
FENDD
FENDU
Earliest End Time
TIMS
6
0
FENDU
SSTAD
Latest Start Date
DATS
8
0
SSTAD
SSTAU
Latest Start Time
TIMS
6
0
SSTAU
SENDD
Latest End Date
DATS
8
0
SENDD
SENDU
Latest End Time
TIMS
6
0
SENDU
ISTAD
Actual Start Date
DATS
8
0
ISTAD
ISTAU
Actual Start Time
TIMS
6
0
ISTAU
IENDD
Actual End Date
DATS
8
0
IENDD
IENDU
Actual End Time
TIMS
6
0
IENDU
PENDD
Forecast End Date
DATS
8
0
PENDD
PENDU
Forecast End Time
TIMS
6
0
PENDU
ISPLI
Actual Number of Splits
DEC
3
0
ISPLI
KPVER
Distribution of Capacity Requirements (Planned/Prodn Order)
CHAR
8
0
TC29
CR_VERTL
OBSTA
Object status (order status)
CHAR
22
0
ONR00
OBSTA
AUFPL
Routing number of operations in the order
NUMC
10
0
CO_AUFPL
APLZL
General counter for order
NUMC
8
0
AFVC
CO_APLZL
PLNUM
Planned Order
CHAR
10
0
PLAF
PLNUM
PLNTY
Task List Type
CHAR
1
0
TCA01
PLNTY
PLNNR
Key for Task List Group
CHAR
8
0
PLNNR
PLNAL
Group Counter
CHAR
2
0
PLNAL
ZAEHL
Internal counter
NUMC
8
0
CIM_COUNT
PLNFL
Sequence
CHAR
6
0
PLNFOLGE
ZAEHF
Internal counter
NUMC
8
0
CIM_COUNT
PLNKN
Number of the Task List Node
NUMC
8
0
PLNKN
ZAEHP
Internal counter
NUMC
8
0
CIM_COUNT
SPLKN
Number of the task list node of the sub-operation
NUMC
8
0
SPLNKN
SZAEHL
Internal counter
NUMC
8
0
CIM_COUNT
SAFNR
Sales Operations Planning Order
CHAR
10
0
SAFNR
VORNR
Operation/Activity Number
CHAR
4
0
VORNR
OTYPE
Object Type
CHAR
2
0
T778O
OTYPE
PERNR
Personnel Number
NUMC
8
0
PERNR_D
CANUMF
Counter for the main capacity requirements record
NUMC
4
0
CANUMF
SPLIT
Split number
INT1
3
0
CY_SPLIT
KBSTA
Status of a Capacity Requirements (Object Number)
CHAR
22
0
ONR00
CY_KBSTA
FSSBD
Earliest scheduled start: Processing (date)
DATS
8
0
FSSBD
FSSBZ
Earliest Scheduled Start: Processing (Time)
TIMS
6
0
FSSBZ
FSSAD
Earliest scheduled start: Teardown (date)
DATS
8
0
FSSAD
FSSAZ
Earliest Scheduled Start: Teardown (Time)
TIMS
6
0
FSSAZ
SSSBD
Latest Scheduled Start: Processing (Date)
DATS
8
0
SSSBD
SSSBZ
Latest Scheduled Start: Processing (Time)
TIMS
6
0
SSSBZ
SSSAD
Latest Scheduled Start: Teardown (Date)
DATS
8
0
SSSAD
SSSAZ
Latest Scheduled Start: Teardown (Time)
TIMS
6
0
SSSAZ
MGVRG
Operation Total Quantity
QUAN
13
3
MGVRG
MEINH
Unit of measure for activity
UNIT
3
0
T006
VORME
RSTUF
Reduction Level Which Reduces Operation Lead Time
NUMC
1
0
RSTUF
PLSCN
Planning Scenario in Long-Term Planning
NUMC
3
0
PLSC
PLSCN
BSTKZ
Capacity Requirement Availability Confirmation Code
CHAR
1
0
CY_BSTKZ
Possible values
Not yet checked or no capacity relevant to finite scheduling
1
Capacity available
2
Missing capacity
3
The requirements record belongs to a dispatched operation
BEDZLF
BEDZL of Main Operation (for Phases and Their Main Ops)
NUMC
8
0
BEDZLF
PHASE_KZ
Indicator: Phase
CHAR
1
0
PHASE_KZ
Possible values
No information about phases exists
0
Operation is not a phase and has no phases
1
Operation has phases
2
Operation is a phase
MAXBD_KZ
Indicator: Capacity fully committed
CHAR
1
0
MAXBD_KZ
ANZMA
Number of employees
DEC
5
2
ANZMS